Sample PMI-SP Exam Questions & Explanations

Practice with real question formats, multiple choice options, and detailed answer explanations for PMI PMI-SP.

Question #1 Verified Q&A
Once the project's WBS has been created what process may happen next?
A Estimate activity durations
B Sequence activities
C Define activities
D Estimate activity resources
Correct Answer: Define activities
Explanation:
The define activities process is the process that may begin once the project's WBS has been completed and approved. It is possible, in some projects, to complete the WBS and the activity list at the same time. Answer option D is incorrect. Sequencing the activities cannot happen until the activity list has been created. Answer option A is incorrect. Estimating activity resources is dependent on the activity list, so this choice is not valid. Answer option C is incorrect. Estimate activity durations are dependent on the activity list, so this choice is not valid.
Question #2 Verified Q&A
Which of the following scheduling techniques identifies the successor activities and the predecessor activities to assist the project manager in sequencing the project work?
A Schedule network template
B Dependency determination
C Precedence Diagramming Method
D Activity on the Node
Correct Answer: Precedence Diagramming Method
Explanation:
The Precedence Diagramming Method uses both predecessors and successors as nodes in the project network diagram. The PDM approach is the most common network diagram approach used. Answer option C is incorrect. Dependency determination identifies the order of the project work. Answer option B is incorrect. The schedule network template is a tool that uses a previous project network diagram as a base for the current project network diagram. Answer option D is incorrect. Activity on the node laces activities on circles within a network diagram. It is an example of the precedence diagramming method.
Question #3 Verified Q&A
You are the project manager of the NHGQ project for your company. You must create and distribute performance reports every week to your key project stakeholders. What communication technique<br />
do you normally use to distribute reports?
A Many-to-many
B One-to-one
C Push technique
D Pull technique
Correct Answer: Push technique
Explanation:
Performance reports are distributed through the push technique. This means that the project manager distributes the reports regularly through a mechanism, such as email. Answer option C is incorrect. One-to-one technique describes a conversation between two people. Answer option B is incorrect. Many-to-many technique describes a conversation between many people. Answer option D is incorrect. A pull technique describes the recipients of the report "pulling" the information, such as from a Website.
Question #4 Verified Q&A
Your project team is executing the project plan and things are going well. Your team has reached its first milestone and is now in the second phase of the project. The project stakeholders have requested that you find a method to reduce the duration of the project. They will reward you and your project team with a 25 percent bonus of the project costs if you can finish the project thirty days earlier than what was already planned. The stakeholders, however, will not approve any additional labor costs as part of the agreement. Which approach could you use to shorten the duration of the project?
A Crash the project schedule.
B Fast track the project.
C Perform resource leveling for the project.
D Remove things from the project scope.
Correct Answer: Fast track the project.
Explanation:
Fast tracking is a technique for compressing project schedule. In fast tracking, phases are overlapped that would normally be done in sequence. It is shortening the project schedule without reducing the project scope. It does not add any additional labor but it can introduce project risks. Answer option D is incorrect. Removing things<br />
from the project scope can reduce the project duration, but it will not satisfy the requirements the<br />
stakeholders have identified. Answer option A is incorrect. Resource leveling can actually increase the project duration. Answer option B is incorrect. Crashing can reduce the project duration but it increases the labor expense, something the stakeholders won't approve.
Question #5 Verified Q&A
The Define Activities process is the first process in the project time management knowledge are
A Milestone list
B Activity attributes
C Activity list
D Project document updates
Correct Answer: Project document updates
Explanation:
Project document updates are not an output of the Define Activities process. Project document updates are the outputs for estimate activity resources. Project document updates include the following: Activity list Activity attributes Resource calendars Answer option A is incorrect. The activity list is an output of the define activities process. Answer option C is incorrect. The activity attributes is an output of the define activities process. Answer option B is incorrect. The milestone list is an output of the define activities process.

Want to practice all 326 questions?

Practice under real exam conditions with instant grading, timed simulations, and community insights.

Start Full PMI-SP Practice Test

Frequently Asked Questions

Common questions about the PMI PMI-SP certification practice test

How many questions are in the PMI PMI-SP practice exam on ExamsQA?
Our PMI-SP (PMI Scheduling Professional Practice Test) practice question bank currently includes 326 verified questions with comprehensive explanations.
Are the PMI-SP exam practice questions up to date for 2026?
Yes, all PMI PMI-SP practice questions are regularly updated and verified against current exam objectives.
Will the PMI-SP practice questions help me pass on my first attempt?
The PMI-SP (PMI Scheduling Professional Practice Test) question bank is built to mirror the real exam's format and topics, with detailed explanations for every answer so you understand the reasoning — not just memorize responses.
Is there a free demo available for PMI-SP PMI Scheduling Professional Practice Test?
Yes, ExamsQA offers free demo questions for the PMI-SP exam so you can test the interface and question quality before purchasing full access.