1
Question
You work as the project manager for Blue Well Inc. You are working with your project team to schedule the days the project work will take place. You have created a project network diagram as shown in the figure:

Exhibit

Based on this diagram, find out the earliest day on which Activity G can be started.
Options
A Day 7
B Day 22
C Day 13
D Day 17
Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

2
Question
You are the project manager of the NHQ project. This project is slightly larger than the GTR project, in which you also served as the project manager. You decide to use the actual activity duration of the GTR project as a basis for your current NHQ project. This, you reason, will save time for your project, as the previous project has provided the information. Which one of the following terms best describes the action you are doing in this scenario?
Options
A You are creating a bottom-up estimate.
B You are relying on expert judgment.
C You are creating an analogous estimate.
D You are creating a rough order of magnitude estimate.
Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

3
Question
You work as a Project Manager for Tech Perfect Inc. You are looking for performance efficiencies of a project. The related key values are provided in the table below:

What will be the cost variance (CV) of the project at the current point of time?
Options
A -80
B -10
C +80
D +10
Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

4
Question
You work as a project manager for BlueWell Inc. Management has asked you to communicate with them whenever your project is about to reach a milestone so that they can review your project performance to date. Where can you find a list of the project milestones to anticipate management's request?
Options
A Milestone list
B Project charter
C Scope baseline
D Project Schedule Management Plan
Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

5
Question
Which of the following are the outputs to the Determine Budget process? Each correct answer represents a complete solution. Choose all that apply.
Select 4
Options
A Scope baseline
B Cost performance baseline
C Project document updates
D Project funding requirements
Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!