Official Bank 0/326

PMI Scheduling Professional Practice Test (PMI-SP) - PMI Exam Questions

Last updated on June 20, 2026

97% Exam Compliance
326 Total Questions
1
Question
Wendy is the project manager for the NHQ project. She is working with her project to begin creating the project duration estimate. Her organization is in weak matrix and several of the project team members are scheduled to complete work on other projects. What input will most likely be of the biggest assistance as Wendy and the project team begin creating the duration estimate for this project?
Options
A Project scope statement
B Project communications management plan
C Project charter
D Resource calendar
Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

2
Question
Which of the following are the outputs to the Determine Budget process? Each correct answer represents a complete solution. Choose all that apply.
Select 4
Options
A Scope baseline
B Cost performance baseline
C Project document updates
D Project funding requirements
Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

3
Question
You work as a project manager for BlueWell Inc. Management has asked you to communicate with them whenever your project is about to reach a milestone so that they can review your project performance to date. Where can you find a list of the project milestones to anticipate management's request?
Options
A Milestone list
B Project charter
C Scope baseline
D Project Schedule Management Plan
Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

4
Question
Which of the following processes fall under the Project Integration Management knowledge area? Each correct answer represents a complete solution. Choose all that apply.
Select 4
Options
A Project Plan Development
B Integrated Change Control
C Quality Assurance
D Project Plan Execution
Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

5
Question
Fill in the blank with the appropriate word. ____ management sets the boundaries for the project and is the foundation on which the other project elements are built.
Reveal Only
Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

Finish Practice?

Are you sure you want to finish? This will end your practice session.