1
Question
You have been asked to be the manager for a governmental portfolio, and your starting point should be tendering a strategic plan to the board for validation and approval for continuation. Which documents/artifacts do you have debuting the portfolio that you can use to develop the strategic plan?
Options
A EEF’s, portfolio component inventory, organizational process assets
B Portfolio charter, portfolio roadmap, organizational strategy and objectives
C Organizational strategy and objectives, inventory of work, portfolio process assets
D Prioritization analysis, portfolio process assets, portfolio roadmap
Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

2
Question
You are managing a complex portfolio with high risk levels due to emerging technological breakthroughs and a short benefit window to market your product. The Portfolio Process Assets are important and referenced throughout the portfolio life cycle. Which of the following is correct regarding the Portfolio Process Assets purpose and focus?
Options
A High-level prioritization mapping of the portfolio
B Corresponds to the means to the “to-be” vision
C Can be used to influence the portfolio’s success
D Forecasts how and when the portfolio will deliver value to the organization
Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

3
Question
Your company got recently acquired by another company and the strategic directions which your portfolio is based on have been changed. Which document do you, as a portfolio manager, update to reflect the change to the timeline?
Options
A Portfolio Management Plan
B Portfolio Roadmap
C Portfolio Strategic Plan
D Communication Management Plan
Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

4
Question
Your company changed its executives due to the lack of benefits realization and previous corruption issues. The new management has informed you that as of now, this will not change any process in the portfolio and everything will remain the same. However, only the risk tolerance for the organization will be impacted, what will you do as a portfolio manager?
Options
A Update the Strategic Plan
B Revise the roadmap to change the timeline due to the new risk profile
C Assess the impact of the change along with the new management
D Perform stakeholders analysis once again and change the organization risk tolerance in the portfolio communication management plan
Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

5
Question
Some of your Stakeholders reported to you that they are not receiving status reports and other regular information on the Portfolio progress. This has caused a big issue with the governance board and they requested an immediate resolution. You have already analyzed the stakeholders and prepared the communication matrix; what is your best course of action in this case?
Options
A Meet individually with each stakeholder and re-analyze their needs and expectations
B Update the communication matrix
C Update the Communication Management Plan
D Correctly configure the PMIS
Discussion (0 comments)