1
Question
Your organization has a defined portfolio management process that it has followed for three years. As the portfolio manager, you keep your various plans up to date, and because of numerous regulatory changes involving the telecom industry, it is time to review and update the risk management plan. You have several key stakeholders working with you as you realize the importance of this plan in maintaining a competitive advantage. One way you and your team are assessing the various risks that may impact the structure of the portfolio is to use:
Options
A Portfolio reports
B Risk metrics
C Weighted ranking and scoring techniques
D Portfolio component charts
Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

2
Question
Risk management is an integral part of project, program and portfolio management and is invoked throughout the project, program and portfolio life cycle. When it comes to managing portfolio risks,

which of the following activities is used
Options
A Risk Assessment and Risk Response
B Risk Assessment
C Risk Planning
D Risk Response
Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

3
Question
Some of your Stakeholders reported to you that they are not receiving status reports and other regular information on the Portfolio progress. This has caused a big issue with the governance board and they requested an immediate resolution. You have already analyzed the stakeholders and prepared the communication matrix; what is your best course of action in this case?
Options
A Meet individually with each stakeholder and re-analyze their needs and expectations
B Update the communication matrix
C Update the Communication Management Plan
D Correctly configure the PMIS
Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

4
Question
You have set a series of meetings with your portfolio team members as an answer to the identification and update of the organization near-term budget and plans. As a result you have defined and developed the portfolio strategic goals, near-term budgets, and plans, and you now want to start managing ongoing portfolio activities. What is the focus of what you are doing?
Options
A All of the options
B Initiating the portfolio
C Achieving Results
D Authorizing the portfolio
Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

5
Question
Assume at this point as the portfolio manager in your mattress company, you are activating portfolio components, updating portfolio reports, and documenting the decisions made at the recent Portfolio

Governance Committee meeting as the company moves into new markets. You are therefore:
Options
A Maintaining a decision log from the Committee meeting
B Authorizing the portfolio
C Updating the portfolio strategic plan
D Communicating decisions to all stakeholders
Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

Finish Practice?

Are you sure you want to finish? This will end your practice session.