1
Question
A user you advise wishes to transfer variable process instructions for automated processing directly to certain work centers and machines in the production department (for example, feed speed, pressing pressure, dry temperature). The user also wishes to receive variable as-is messages (such as actual quantities, actual times) from these work centers and machines and to process these messages for feedback concerning production orders. Which of the following options would you recommend to implement these requirements?
Options
A Execution Steps (XSteps) and process messages
B SAP Application Link Enabling (ALE)
C Plant data collection (PP-PDC) interface
D SAP Business Intelligence (BI)
Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

2
Question
Which functions can be triggered before releasing a production order? (Choose three)
Select 3
Options
A Selection of a routing
B Confirmation
C Stock determination
D Selection of a BOM
E Scheduling
Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

3
Question
Which property applies for consumption with planning strategy 40 (planning with final assembly)?
Options
A Consumption can result in subsequent adjustments of planned receipts.
B Consumption creates a static and binding assignment between the planned independent requirements and the customer requirements for the entire procurement process.
C Consumption takes place with the planning material.
D Consumption can reduce the originally planned production quantity.
Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

4
Question
After a material has been included in a NETCH material requirements planning run you change its BOM (bill of materials).

Which of the following planning file entries for this material are set by the system?
Options
A The BOM explosion and the NETPL planning indicator
B The NETCH and NETPL planning indicators
C The BOM explosion, the NETCH, and the NETPL planning indicators
D The BOM explosion indicator
Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

5
Question
The stock/requirements list for a finished product contains only one sales order and one fixed planned order with the same quantity. The availability dates for both MRP elements are on working days. The availability date for the fixed planned order is set to a later date than the one for the sales order. However, a corresponding rescheduling exception message does not appear.

What could be the reasons? (Choose two)
Select 2
Options
A The delta between the availability dates falls within the tolerance window defined in Customizing.
B The MRP elements are linked via fixed pegging.
C Requirements planning has not been carried out.
D The fixed planned order is outside the rescheduling horizon.
Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!