Official Bank 0/278

PMI Risk Management Professional Exam (PMI-RMP) - PMI Exam Questions

Last updated on June 22, 2026

97% Exam Compliance
278 Total Questions
1
Question
A risk manager schedules workshops for identifying risks about an initiative involving multiple business units, recruitments for different roles, procurements, technological uplift, training, and changes in the ways of working. Who should participate in the risk management activity?
Options
A Core project team
B Internal stakeholders only
C Internal and external stakeholders
D Key business stakeholders
Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

2
Question
While implementing the risk response plan for a previously identified risk, some secondary risks
were identified but not captured on the risk register. The project manager decided to review the risk management plan to ensure this does not happen for future, similar situations.

What should the project manager do next?
Options
A Identify secondary or residual risks for associated risk plans.
B Monitor and control secondary and residual risks in the risk register.
C Develop risk response plans for all identified risks.
D Update the communications management plan to avoid future issues
Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

3
Question
A project manager of an IT company is assigned to a project whose schedule may be delayed due to a lack of resources to conclude the backlog activities. The project manager decides to hire additional developers to reduce the project's technical debt and meet the project deadline.

What should the risk manager advise the project manager to do to address this situation?
Options
A Immediately hire as soon as the project begins to fall behind schedule.
B Only hire if risk response is escalated and approved by the stakeholders.
C Hire as soon as the project metrics trigger a risk response.
D Only hire when it is economically feasible to do so.
Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

4
Question
A project team has just completed a project plan, which includes extra days for most of the critical activities to cover any possible issues. Stakeholders want to remove these additional days, because the end date is longer than expected.

What should the risk manager do first?
Options
A Remove the activity padding.
B Update the schedule constraints.
C Review the risk response plan.
D Update the risk contingency plan.
Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

5
Question
A risk manager has been assigned to replace a risk manager on sick leave. The new risk manager notices that the risk register is missing data that are key to the risk management process.

Which data will the risk manager require first?
Options
A Risk description risk response, and quantitative data
B Risk description, risk probability, and risk impact
C Project plan, risk complexity, and secondary risk
D Project plan, risk priority, and tool availability
Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

Finish Practice?

Are you sure you want to finish? This will end your practice session.