Official Bank 0/278

PMI Risk Management Professional Exam (PMI-RMP) - PMI Exam Questions

Last updated on June 22, 2026

97% Exam Compliance
278 Total Questions
1
Question
A core project team is working on unrelated tasks in advance to reduce the risk of delay due to an external team not completing its tasks on time. The core project team has completed all possible unrelated tasks but cannot move forward, because the external team's tasks have yet to be completed.

What should the risk manager do next?
Options
A Start a quantitative analysis to understand the impact.
B Ask the risk owners to review the risk response plan.
C Crash the schedule to mitigate the risk consequences.
D Transfer the risk to the external team.
Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

2
Question
After a number of risk workshops, risks have been identified. Which is the first element the risk owner should look for in the response plan to help mitigate the risks?
Options
A Probability of a response triggering a secondary risk
B Verify due dates for the actions have been identified
C How the response will affect the quality of the components
D If the risk response is tied to an activity on the critical path
Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

3
Question
While planning for project execution phase stakeholders are making decisions on how to respond to
known and new risks. What artifact should the stakeholders prepare?
Options
A Issue log
B Risk-adjusted back log
C Change log
D Assumption log
Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

4
Question
A project team has just completed a project plan, which includes extra days for most of the critical activities to cover any possible issues. Stakeholders want to remove these additional days, because the end date is longer than expected.

What should the risk manager do first?
Options
A Remove the activity padding.
B Update the schedule constraints.
C Review the risk response plan.
D Update the risk contingency plan.
Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

5
Question
A risk manager schedules workshops for identifying risks about an initiative involving multiple business units, recruitments for different roles, procurements, technological uplift, training, and changes in the ways of working. Who should participate in the risk management activity?
Options
A Core project team
B Internal stakeholders only
C Internal and external stakeholders
D Key business stakeholders
Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

Finish Practice?

Are you sure you want to finish? This will end your practice session.