Official Bank 0/278

PMI Risk Management Professional Exam (PMI-RMP) - PMI Exam Questions

Last updated on June 22, 2026

97% Exam Compliance
278 Total Questions
1
Question
What is an example of legal and regulatory requirements and/or constraints when assessing a project environment for threats and opportunities?
Options
A Organizational communication requirements
B Confidentiality of project information
C Organizational standard policies, processes, and procedures
D Formal knowledge sharing and information sharing procedures
Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

2
Question
A project team is presenting a delivery plan to a client. Some of the client's experts do not feel comfortable with some activities at a critical stage. The experts ask to change the plan and present a better alternative.

What should the risk manager do first?
Options
A Review and update the project quality management plan.
B Add additional time to the delivery plan to cover issues.
C Conduct a risk assessment process for the critical stage.
D Create a more detailed work breakdown structure (WBS).
Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

3
Question
After a number of risk workshops, risks have been identified. Which is the first element the risk owner should look for in the response plan to help mitigate the risks?
Options
A Probability of a response triggering a secondary risk
B Verify due dates for the actions have been identified
C How the response will affect the quality of the components
D If the risk response is tied to an activity on the critical path
Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

4
Question
A risk manager has been assigned to replace a risk manager on sick leave. The new risk manager notices that the risk register is missing data that are key to the risk management process.

Which data will the risk manager require first?
Options
A Risk description risk response, and quantitative data
B Risk description, risk probability, and risk impact
C Project plan, risk complexity, and secondary risk
D Project plan, risk priority, and tool availability
Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

5
Question
While implementing the risk response plan for a previously identified risk, some secondary risks
were identified but not captured on the risk register. The project manager decided to review the risk management plan to ensure this does not happen for future, similar situations.

What should the project manager do next?
Options
A Identify secondary or residual risks for associated risk plans.
B Monitor and control secondary and residual risks in the risk register.
C Develop risk response plans for all identified risks.
D Update the communications management plan to avoid future issues
Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

Finish Practice?

Are you sure you want to finish? This will end your practice session.