1
Question

Which of the following Is an example of tasks most associated with the test design activity?

Select 3
Options
A

Test data, derived from production data, is developed for use during testing

B

The project manager updates the project schedule as key test tasks are completed

C

The Identification of test execution and test automation tools

D

Every day, the tester notes the status of his/her test cases in preparation for daily reports

Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

2
Question

Consider the following excerpt from a test report 'We tested the module AX45T and we got only 1 failure. To recreate the failure, we used test file PR624_DR78_TCB0022 pkr, available under the PR624_DR78 repository in the CK01 server". Which incident report objective does this excerpt satisfy?

Options
A

Provides developers with information to isolate the failure.

B

Does not belong to an incident report

C

Provides Project Managers with information on the project risks.

D

Provides test managers with information to report test progress.

Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

3
Question

What is static analysis?

Options
A

The decision between using white or black box test techniques.

B

Executing software to validate the most common path through the code.

C

A technique to find defects in software source code and software models, performed without executing code.

D

It is a testing technique used during system testing.

Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

4
Question

Which of the following statements correctly describe Black-Box Testing''

Options
A

Test on an individual software component in isolation from other components, to avoid external influence

B

Tests that investigate the input vs. trfe output behavior of a software system.

C

Test derived from the ability of the testers and their intuition and experience with similar applications and technologies (sometimes used to strengthen systematic techniques)

D

Test of the interfaces between components and of the interactions with different parts of a system

Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

5
Question

An Incident Management tool implements the following defect states Open. Assigned. Solved. Closed. Consider the following defect report: Id: T000561 Test Object: "Warehouse Management" application Tester name : John Bishop Date: 10th, April 2010 Test Case MRT5561 Status: OPEN Severity Serious Priority: Problem : After inputting the Total Quantity item = 450 in the SV034 screen . the system shows an unexpected Error message = 47 Correction: Developer name: Closing date Which of the following is a valid criticism of this report?

Select 47
Options
A

The Priority, the Correction description and the Developer name are missing

B

The description is not highlighting the source of the problem

C

The version of the application is missing

D

There is no link to the applicable requirement (traceability)

Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

Finish Practice?

Are you sure you want to finish? This will end your practice session.