Official Bank 0/259

PMI Risk Management Professional Exam (PMI-RMP) - PMI Actual Exam Questions

Last updated on May 13, 2026

97% Exam Compliance
259 Total Questions
1
Question

When conducting a risk identification exercise, what two actions should the risk manager take? (Choose two.)

Select 2
Options
A

Request a contingency reserve from management

B

Arrange a team meeting, review the project's scope, and discuss dependency mapping

C

Ensure participants review relevant documents before attending the meeting

D

Ensure that all the relevant stakeholders participate

E

Update the risk register during the team meeting.

Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

2
Question

The risk manager notices that in their workshops, most of the risks identified are threats. What should the risk manager do to increase the number of opportunities identified?

Options
A

Use the Delphi technique involving experts who have identified opportunities in the past

B

Interview more stakeholders who have a positive mindset

C

Conduct a strengths, weaknesses, opportunities, and threats (SWOT) analysis

D

Conduct a political, economic, sociological, technological, legal, and environmental (PESTLE) analysis

Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

3
Question

A risk manager for a cross-functional project is initiating the risk identification process. The risk manager conducted some meetings for stakeholders to express their concerns, but some stakeholders are complaining that their opinions were not considered. How should the risk manager address these concerns?

Options
A

Refer to the requirements documentation to confirm stakeholder requirements as they relate to risks.

B

Refer to the project charter to find guidelines and stakeholder communication channels.

C

Review the stakeholder register and stakeholder engagement plan to communicate and solicit stakeholder input.

D

Rewrite the risk register to include the additional possible risks and inform the stakeholders.

Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

4
Question

After completing the risk register, many team members feel there is a lack of time prioritization for one of the identified risks What are the team members referring to?

Options
A

Risk trigger

B

Risk escalation

C

Risk urgency

D

Risk time impact

Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

5
Question

Stakeholder holiday schedules and availability of raw materials were two risks initially identified in a manufacturing project. The risk manager now notices that both risks are not quite as originally described and might require a plan change. What should the risk manager do next?

Options
A

Consult with the project manager to agree that these risks should be removed from the risk register

B

Keep the risks in the risk register and continue to follow up until the change actually takes place.

C

Identify workarounds that can be implemented whether or not the change takes place.

D

Revisit the project the assumptions and constraints to potentially update the risk impact and response.

Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

Finish Practice?

Are you sure you want to finish? This will end your practice session.