Official Bank 0/612

PMI Scheduling Professional Practice Test (PMI-SP) - PMI Actual Exam Questions

Last updated on May 12, 2026

97% Exam Compliance
612 Total Questions
1
Question

Della works as a Project Manager for Blue Well Inc. A number of projects are running under her guidance. You, being a team leader of a project, provide Della the performance indexes of your project. The schedule variance (SV) of your project is zero. What does this figure depict?

Options
A

Planned Value (PV) If the resulting schedule is negative, it indicates that the project is behind schedule. A value greater than 0 shows that the project is ahead of the planned schedule. A value of 0 indicates that the project is right on target. Answer option C is incorrect. The negative SV means that project is behind the schedule. Answer option D is incorrect. This result can be drawn by looking at the cost variance (CV) of the project. Answer option B is incorrect. The positive SV depicts that the project is ahead of the planned schedule.

B

Project is right on target.

C

Project is ahead of the schedule.

D

Project is behind the schedule.

E

Costs are higher than planned.

Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

2
Question

Amy is working on a project which is forty percent complete though it was scheduled to be fifty percent complete as of today. Management has asked Amy to report on the schedule variance for her project. If Amy's project has a BAC of $750,000 and she has spent $485,000 to date, what is the schedule variance value?

Options
A

-$75,000

B

-$42,000

C

-$45,000

D

-$65,000

Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

3
Question

You are the project manager of the NHT Project. This project has 12,345 office doors to install throughout a campus. Each of the doors costs the project $456 and requires special hardware to electronically lock and open the doors. You've gathered the project team before they begin the installation for a hands-on training. As a group you and the project team install 50 doors following a checklist of instructions so that every door will be installed exactly the same throughout the campus and with minimal waste. This is an example of what project execution technique? was asking for a project execution activity. Preventive and corrective actions are part of project execution. Answer option D is incorrect. Quality control is a controlling and monitoring process, not an executing process. Answer option B is incorrect. The defect repair validation comes after the project team has corrected an error

Options
A

something that has not occurred in this instance. Answer option C is incorrect. Corrective action is a response to something that needs to be corrected in the project.

B

Preventive action

C

Defect repair validation

D

Implemented corrective action

E

Quality control

Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

4
Question

You are the project manager of the NHA Project. This project is expected to last one year with quarterly milestones throughout the year. Your project is supposed to be at the third milestone today, but you are likely to be only 60 percent complete. Your project has a BAC of $745,000 and you have spent $440,000 of the budget-to-date. What is your cost variance for this project?

Options
A

11,667

B

$-111,750

C

There is no variance.

D

$7,000

Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

5
Question

Frank is the project manager of a construction project. In this project, Frank has elected to allow the interior design phase of the project to overlap with the pool construction phase of the project. Normally, Frank would not allow these two phases to overlap, but for this project, he has elected to do so in order to compress the project schedule. What is this schedule compression technique called?

Options
A

Resource leveling heuristic

B

Lead time

C

Fast tracking

D

Crashing

Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

Finish Practice?