SAP Certified Application Associate - Production Planning & Manufacturing with SAP ERP 6.0 EHP7 (C_TSCM42_67) - SAP Actual Exam Questions
Last updated on May 01, 2026
The master data for an in-house production process is to be set up in the SAP ECC system. To do this, you should create a suitable routing that plans for five operations in an initial sequence (10, 20, 30, 40, 50). There should be an option of relocating operations 30 and 40 to a second sequence on other work centers if there are capacity bottlenecks. What sequence type would you use to create the second sequence in the system?
Substitute sequence
Alternative sequence
Parallel sequence
Standard sequence
to join the discussion
No discussions yet. Be the first to ask!
Delete Comment
Are you sure? This action cannot be undone.
You create a routing that includes five operations in an initial sequence (10, 20, 30, 40, 50). When capacity bottlenecks occur, you want to use a second sequence on other work centers for operations 30 and 40. Which sequence category do you use to create the second sequence in the system?
Finish-start relationship
Standard sequence
Parallel sequence
Alternative sequence
to join the discussion
No discussions yet. Be the first to ask!
Delete Comment
Are you sure? This action cannot be undone.
Which of the following functions are available in SAP ECC when using capacity leveling? (Choose three)
Batch size optimization
Midpoint scheduling
Lot size optimization
Finite capacity scheduling
Setup time reduction
to join the discussion
No discussions yet. Be the first to ask!
Delete Comment
Are you sure? This action cannot be undone.
Which objects can affect the calculation of capacity requirements for an operation? (Choose three)
Standard values (routing)
In-house production time (material master)
Transport time (routing)
Formulas (work center)
Operation control key (routing)
to join the discussion
No discussions yet. Be the first to ask!
Delete Comment
Are you sure? This action cannot be undone.
Which of the following statements is true for the ATP (available to promise) availability check in SAP ECC that is triggered from a customer order?
The ATP check does not confirm against stocks and receipts, it checks consumption against planning requirements.
An availability check by means of ATP creates fixed links between customer orders and their confirmed receipts.
The ATP quantity is the quantity still available that can be used to confirm incoming customer orders.
If the ATP check establishes non-availability, it checks whether it is still possible to procure or produce in time.
to join the discussion