Official Bank 0/453

Program Management Professional (PgMP) Exam (PGMP EXAM DUMPS 2026) - PEGA Actual Exam Questions

Last updated on May 01, 2026

97% Exam Compliance
453 Total Questions
1
Question

A software deployment program for a multinational organization requires the engagement of subcontractors. During the program planning phase, the contracts manager informs the program manager that the primary subcontractor's agreement includes incentives that would potentially conflict with program objectives. What should the program manager do first?

Options
A

Review the contracts, and create a program budget contingency.

B

Draft a change request for approval by the program steering committee.

C

Ask the program management office (PMO) to conduct a risk assessment.

D

Review the program charter, and update program objectives accordingly.

Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

2
Question

Complete the following phrase about quality management: Quality is into a program, not into a program.

Options
A

Built, inspected

B

Planned, inspected

C

Planned, controlled

D

Executed, controlled

Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

3
Question

Tom is program manager for his organization. His program is scheduled to last ten months and has a cost estimate for the program of $550,000. It is now month nine and Tom reports that he actually has a cost variance of a positive $56,000. While Tom is pleased, the new management is not. Why is a positive cost variance not necessarily good news?

Options
A

A poor cost estimate prevented the organization from adding things to the program scope.

B

Tom has overestimated the cost of the program.

C

A poor cost estimate could affect the organization's decisions to invest the funds elsewhere .

D

Tom has forgot to include deliverables in the program.

Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

4
Question

The program manager must define the program and understand the organization’s target market and customer needs. What should the program manager do first?

Options
A

Brainstorm with the program team to decide on the definitions of the target market.

B

Meet with peers to identify the company’s competitors in the target market.

C

Meet with the project managers to identify the target market.

D

Work with the program sponsor to assess the needs of the target market.

Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

5
Question

You are the program manager for your organization and are planning the roles and responsibilities in your program. You would like to create a RACI chart for the program work. What does RACI mean?

Options
A

It is a roles and responsibilities chart that uses responsible, accountable, consult, and inform responsibilities as the chart legend.

B

It is a roles and responsibilities chart that uses responsible, action, consult, and interest responsibilities as the chart legend.

C

It is a roles and responsibilities chart that uses resource, action, contribute, inform responsibilities as the chart legend.

D

It is a roles and responsibilities chart that uses responsible, accountable, contribute, and inform responsibilities as the chart legend.

Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

Finish Practice?

Are you sure you want to finish? This will end your practice session.