1
Question

When planning and implementing a SAM project why are Key Performance Indicators (KPIs) so valuable?

Options
A

They allow Internal Audit to view all software keys in the business

B

Because they enable the project manager to view the overall success of the SAM project

C

Key Performance Indicators highlight any mistakes that have been made during the project

D

They allow external bodies to understand a company performance.

Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

2
Question

Which of the following statements is TRUE? 1.SAM Processes do not relate to in-house developed software because there are no licensing issues 2.SAM processes relate to all areas apart from network equipment because network software is not licensed

Options
A

Both of them

B

2 only

C

Neither of them

D

1 only.

Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

3
Question

Which of the following BEST describes the objective of the Core Asset Management processes?

Options
A

To maintain information about software assets throughout their lifecycle and to manage the physical assets related to software

B

To manage all software assets and their licenses.

C

To manage all software and hardware assets

D

To identify and maintain information about all software assets throughout their lifecycle.

Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

4
Question

Which of the following BEST describes the process of license novation?

Options
A

SAM team must inform re-seller that license has been transferred to another department.

B

Software manufacturer allows usage rights to be changed.

C

Software manufacturer allows ownership in unwanted software licenses to be sold to another organisation

D

Software manufacturer allows the transfer of software licenses and contracts when an organisation reforms itself or restructures.

Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

5
Question

Which of the following should be considered when outsourcing elements of the SAM processes? 1.The conflicts of interest regarding asset information 2.The ownership of software licenses 3.The Software development costs

Options
A

All of them.

B

1 and 3.

C

1 and 2.

D

2 and 3.

Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

Finish Practice?