Professional in Project Management (PPM) (PPM-001) - GAQM Actual Exam Questions
Last updated on April 25, 2026
Which analysis uses beta and triangular distributions as a tool and technique?
Quantitative risk analysis
Qualitative risk analysis
Perform quality assurance
Perform quality control
to join the discussion
No discussions yet. Be the first to ask!
Delete Comment
Are you sure? This action cannot be undone.
Resource reallocation from non critical to critical activities is an example of which Project Scheduling technique:
Critical Path Method
Schedule Compression
Resource Leveling
What if Analysis
to join the discussion
No discussions yet. Be the first to ask!
Delete Comment
Are you sure? This action cannot be undone.
Which tools or techniques will the project manager use for developing the project team?
Negotiation
Roles and responsibilities
Recognition and rewards
Prizing and promoting
to join the discussion
No discussions yet. Be the first to ask!
Delete Comment
Are you sure? This action cannot be undone.
A work package has been scheduled to cost $1,000 to complete, and was to be finished today. As of today, the actual expenditure is $1,200 and approximately half of the work has been completed. What is the cost variance?
-$700
-$200
+$200
+$500
to join the discussion
No discussions yet. Be the first to ask!
Delete Comment
Are you sure? This action cannot be undone.
Which of the following inputs is required for the WBS creation?
Project Quality Plan
Project Schedule Network
Project Management Software
Project Scope Management Plan
to join the discussion
No discussions yet. Be the first to ask!
Delete Comment
Are you sure? This action cannot be undone.