1
Question

Which analysis uses beta and triangular distributions as a tool and technique?

Options
A

Quantitative risk analysis

B

Qualitative risk analysis

C

Perform quality assurance

D

Perform quality control

Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

2
Question

Resource reallocation from non critical to critical activities is an example of which Project Scheduling technique:

Options
A

Critical Path Method

B

Schedule Compression

C

Resource Leveling

D

What if Analysis

Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

3
Question

Which tools or techniques will the project manager use for developing the project team?

Options
A

Negotiation

B

Roles and responsibilities

C

Recognition and rewards

D

Prizing and promoting

Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

4
Question

A work package has been scheduled to cost $1,000 to complete, and was to be finished today. As of today, the actual expenditure is $1,200 and approximately half of the work has been completed. What is the cost variance?

Options
A

-$700

B

-$200

C

+$200

D

+$500

Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

5
Question

Which of the following inputs is required for the WBS creation?

Options
A

Project Quality Plan

B

Project Schedule Network

C

Project Management Software

D

Project Scope Management Plan

Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!