Official Bank 0/120

Certified Lean Six Sigma Yellow Belt (CLSSYB) - GAQM Actual Exam Questions

Last updated on April 25, 2026

97% Exam Compliance
120 Total Questions
1
Question

Cycle Time, Defects, Scrap Cost and Safety are examples of business metrics or commonly referred to as which of the following?

Options
A

Defects per Unit

B

Key Performance Indicators

C

Impediments to Flow

D

Hidden Costs

Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

2
Question

At the beginning of a project we must keep in mind there are basically three views of a process: What you THINK it is, What the SUPPLIER wants and What it SHOULD be.

Options
A

True

B

False

Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

3
Question

A 5 Why Analysis is used to help identify possible defect causes when which one of the below listed tools is created?

Options
A

Fishbone Diagram

B

SIPOC

C

X-Y Matrix

D

Pareto Chart

Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

4
Question

One of the primary deliverables from performing a SIPOC is to begin to understand which inputs have the greatest affect on the ____________ most valued outputs.

Options
A

Business’s

B

Employee’s

C

Management’s

D

Customer’s

Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

5
Question

The Pareto Chart is a tool that displays data that typically follows what ratio?

Options
A

70:30

B

80:20

C

90:10

D

95:5

Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

Finish Practice?

Are you sure you want to finish? This will end your practice session.