which has led to significant improvements. The management team would like to build on this success and develop and implement a supplier management process. You have recently joined the corporate IT department and have been given the results of the survey carried out by the management team.
Refer to Scenario
Which one of the following options is the BEST sequence of activities to adopt in order to implement a supplier management process and to bring the current situation under control?
2. Design and develop a supplier management process.
3. Use the results of the survey to categorize each supplier to determine the type of relationship
required.
4. Establish and populate a SCMIS from the survey feedback.
5. Agree which individuals in the corporate IT department and local IT teams are accountable for the
management of each supplier.
6. Deploy the process in all countries and conduct a program of awareness and training.
7. Identify where there are duplicate or multiple contracts in place with suppliers and instigate an
initiative to review these with the relevant suppliers.
2. Establish and populate the SCMIS from the results of the exercise.
3. Design and develop a supplier management process.
4. Define and agree a supplier policy.
5. Appoint a supplier manager from the corporate IT department to manage all contracts and all
suppliers.
6. Deploy the process in all countries and conduct a program of awareness and training.
7. Renew all contracts to try to obtain better terms and conditions.
2. Define and agree a supplier policy.
3. Use the results of the survey to categorize each supplier to determine the type of relationship
required.
4. Establish and populate a supplier and contract management information system (SCMIS) from the
survey feedback.
5. Deploy the process in the corporate IT department as a pilot.
6. Agree which individuals in the corporate IT department and local IT teams are accountable for the
management of each contract and supplier.
7. Deploy the process in the remaining countries and conduct a program of awareness and training.
2. Agree which individuals in the corporate IT department and local IT teams are accountable for the
management of each supplier.
3. Use the results of the survey to categorize each supplier to determine the type of relationship
required.
4. Establish and populate a SCMIS from the survey feedback.
5. Design and develop a supplier management process.
6. Deploy the process in all countries and conduct a program of awareness and training.
7. Work with the service level manager to ensure that all contracts correctly underpin service level
agreements.
to join the discussion
No discussions yet. Be the first to ask!
Delete Comment
Are you sure? This action cannot be undone.
which were related to a lack of capacity, have occurred during exceptional peak holiday booking periods. The IT organization is not certain when or if these are going to occur in the future. Some booking periods are predictable, such as those associated with promotional offers. Other patterns are totally unpredictable as they often coincide with bad weather being experienced where customers live. You have been asked how the activities of demand management, based on ITIL practices, can be used to address this issue.
Refer to Scenario
Which one of the following options is the BEST set of actions required to resolve the issue?
Gain an understanding of how the PBA relate to the use of the IT assets especially the hardware and software that may be the cause of the IT failures.
Once these activities have been completed, the PBA will be used to plan and implement sufficient capacity to meet all demand at all times.
Discuss the risks associated with failing to meet demand with capacity management and technical staff. Reach agreement on how to avoid a repeat of the IT failures caused by demand at busy periods.
frequency and location of staff activity. Document these as PBA.
Gain an understanding of the different roles that are performed by the call centre staff and how these relate to the PBA for the call centre business processes.
Use this information to identify any shortfall in capacity and create cost estimates of additional resource required to enable the IT services to meet the PBA.
Discuss the risks associated with failing to meet demand with the business managers. Reach agreement on how to avoid a repeat of the IT failures caused by demand at busy periods.
frequency and location of staff activity. Document these as patterns of business activity (PBA) Gain an understanding of the different roles that are performed by staff from all business units and how these relate to the PBA for all business processes.
Use this information to identify any shortfall in capacity and create cost estimates of additional resource required to enable the IT services to meet the PBA.
Recommend that, where PBA are very predictable, investment should be made in additional resource.
Where PBA are unpredictable, the risks associated with railing to meet demand should be discussed
with the business managers, and mitigation actions agreed.
The demand manager should initiate an activity to identify and understand user profiles resulting
from business use of the IT services. Code the user profiles linking them to the associated business
roles.
Match the user profiles to the IT services and analyze any shortfall in capacity required to meet the business objectives. Create a business case for the additional resource required to exceed the business demand for the IT services to account for unpredictable business activity.
Work with service portfolio management and financial management to agree on the approval of the investment and initiate the project to acquire all the additional resources.
to join the discussion
No discussions yet. Be the first to ask!
Delete Comment
Are you sure? This action cannot be undone.
The following services are under review:
• Service 1: Web ordering service. This is a new service that will enable the company to fulfill its
strategy to sell products on-line and increase its customer base by 20%. Only high-level business
requirements have been established so far but. if the project goes ahead, the system will be provided by a supplier using standard applications and technology. A business case has been created which shows the ratio of value-to-cost to be much greater than one.
• Service 2: Sales office service. The service has grown from a number of separate applications that
have been combined into one suite. The technical solution for each application is similar but some use different versions of the same operating system. The applications themselves provide the required utility and support their business outcomes well. There is some overlap in functionality across the set of applications contained in the service suite.
• Service 3: Finance reporting service. The service is used by the finance department to create
statutory reports to fulfill legal obligations. The service is hosted on a legacy system. The cost of supporting the service is increasing gradually and the return obtained from the service is decreasing. Eventually the service will be replaced by the new enterprise resource planning (ERP) service. It is projected that, over the next two years, the ratio of value-to-cost will drop to less than one.
• Service 4: This is a new ERP service that is being implemented across all companies in the
corporate group. It will eventually replace many existing services including the finance reporting
service. The service has been approved and chartered, and has a current status of "design". A large
number of assets have been allocated to this project. As this service is mandated by the corporate owners, no further decision is required.
Refer to Scenario: As part of the service portfolio management team you have been asked to recommend whether investments should be made in these services in the next year.
Which of the following options is the BEST set of decisions to make for the services?
Service 2 - rationalize. Set up a project to identify the best way of retaining the support of the
business outcomes but eliminating the duplication of functionality and supporting components
Service 3 - delay decision. It is likely that this service will be retired, but not yet. The retirement
project will use assets that will be allocated elsewhere this year. Reconsider at next annual review.
Service 2 - retain. Keep the service and support
Service 3 - delay decision. It is likely that this project will use assets that will be allocated review.
Allocate resources to the transition stage of the it in its current form service will be retired, but not yet. The retirement elsewhere this year. Reconsider at next annual
project
Service 2 – re-factor. Set up project to redesign the applications to concentrate on the core
functionality of the service
Service 3 - retain. As the service is needed to fulfill legal and statutory compliance it should be
retained.
Service 2 - replace. Set up project to replace the set of applications with a single application designed
to support the business outcomes
Service 3 - retire. Mark the service for retirement and set up a retirement project. This will make best
use of resources and ensure that information is migrated to the ERP service.
to join the discussion
No discussions yet. Be the first to ask!
Delete Comment
Are you sure? This action cannot be undone.
service management consultant to assess why the IT services were performing poorly and to rectify
the situation. As part of the solution, the consultant implemented service level management and adopted the role of interim service level manager. Service level agreements were negotiated with the business and agreed. The necessary underpinning agreements were negotiated and put in place. Regular monitoring and reporting was implemented. Monthly service review meetings with the business unit managers were established to discuss IT service performance and any issues and improvements. Within a year of the start of the initiative the gift ordering website IT service was performing at
98.7% availability, a significant improvement.
This month's service review meeting was attended by the chief executive officer (CEO) after concerns were expressed about the most recent availability figure for the customer payments service, which
was 94%. This covered the period which included one of the traditionally most popular gift ordering
times. The consultant stated that the poor availability was almost entirely due to an incident that occurred during one of the busiest periods and. as a result, the overall monthly availability percentage was low. Initial investigation has shown that the service desk used the SLA to designate the incident as a 'Priority 2'. This was however lower than the 'Priority 1" the business believed the incident should have been. The subsequent delay in restoration of the service meant some customer orders were lost. The CEO reminded the consultant that a repeat of such an incident would not only have a major effect on monthly revenues but also seriously affect the company's reputation. The consultant agreed that this was unacceptable and committed to review this issue and report back to the CEO.
Refer to Scenario
to join the discussion
No discussions yet. Be the first to ask!
Delete Comment
Are you sure? This action cannot be undone.
Which one of the following options provides the BEST description of the areas that should be addressed by the requirements specification for the new tool?
to join the discussion
No discussions yet. Be the first to ask!
Delete Comment
Are you sure? This action cannot be undone.
Finish Practice?
Are you sure you want to finish? This will end your practice session.