1
Question

What is time-boxing?

Options
A

A period of intense activity within a particular release.

B

Setting an upper time limit and planning the activities within that limit.

C

Tight planning focused on reducing the time required for any activity.

Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

2
Question

The team determines that it has over-committed itself for a Sprint. Who should be present when reviewing and adjusting the Sprint work?

Options
A

The team, the Scrum Master and the Product Owner. The Stakeholders should be consulted.

B

The team and the Scrum Master. The Product Owner should be consulted.

C

The team only. The Product Owner should be consulted.

Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

3
Question

A Project Manager wants to track not just the rate of progress against tasks, but also the overall morale and happiness of the Scrum team. What device will help track morale and happiness?

Options
A

A Gross Happiness index

B

A Niko-niko calendar

C

An employee satisfaction survey

Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

4
Question

A story was estimated at eight ideal hours. A working day is eight hours. Developers can get about six hours of work done on a daily basis. What is the elapsed time required to complete the story?

Options
A

1.25 days

B

1.33 days

C

2 days

D

This cannot be determined without knowing the velocity.

Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

5
Question

A Scrum team failed to meet the Sprint objectives. One of the key members of the team fell ill and was away for two days right at the beginning of the four week Sprint. What is the most likely reason that the team did not meet the Sprint objectives?

Options
A

The Product Owner is unable to prioritize.

B

The team is lacking skills.

C

The team did not plan the Sprint effectively.

D

The team is over-worked.

Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

Finish Practice?

Are you sure you want to finish? This will end your practice session.