ISTQB-BCS Certified Tester Advanced Level- Test Manager (2012) (TM12) - BCS Exam Questions

Last updated on June 20, 2026

97% Exam Compliance
65 Total Questions
1
Question
During the system testing phase a tester from your test team observes a failure in the system under test and he/she decides to create an incident report. The incident report is currently in a “new” state, indicating it needs to be investigated.

Which THREE of the following information items can’t yet be present in the incident report? Number of correct responses: 3 (2 credits out of 3 credits correct, 1 credit point)
Select 3
Options
A What really caused the failure (actual cause)
B The type of defect that caused the failure
C The actual and the expected result highlighting the failure
D Steps to reproduce the failure, including screenshots, database dumps and logs where applicable
E The lifecycle phase in which the defect has been introduced
Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

2
Question
You are performing a quality risk analysis for a CSCI (Computer Software Configuration Item) used to implement a CBIT (Continuous Built-In Test) module of a safety-critical system. During the quality risk analysis you are trying to identify the ways in which failures of the CBIT module can occur, for each of them trying to determine the potential causes and likely effects, and the risk level (calculated as the product of three factors: severity, occurrence and detection).

Which of the following risk analysis techniques are you working with? Number of correct responses: 1
Options
A Cost of Exposure
B A lightweight product risk analysis technique
C Failure Mode and Effect Analysis
D Wide Band Delphi
Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

3
Question
In the test strategy document your organization declares:

- to adopt a V-model development lifecycle, with three formal levels of testing: unit, integration and
system testing

- to use a blended risk-based and regression-averse testing strategy for each level of testing
The following is an excerpt of the “approach” section for the system test plan document of a new project: “Testing will only use manual tests. Due to the short period of time for test execution, the following activities will be performed in parallel with test execution: Test planning, test analysis and test design. Basic metrics will be taken for test effort (i.e. person-hours), test cases executed (passed/failed), and incidents (no more metrics, such as code coverage, will be collected).” In the system test plan, no deviations from the test strategy are described. Based only on the given information, which of the following statements is true? Number of correct responses: 1
Options
A The approach described the system test plan document is inconsistent with both the risk-based and regression testing strategies
B The approach described in the system test plan document is consistent with the test strategy
C The approach described in the system test plan document is consistent with the risk-based testing strategy, but it is inconsistent with the regression testing strategy
D The approach described in the system test plan document is consistent with the regression testing strategy, but it is inconsistent with the risk-based testing strategy
Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

4
Question
During the follow-up phase the following conditions are checked: X1. The code has been completely reviewed X2. All the identified defects have been correctly fixed and the modified code has been compiled successfully and run through all the static analyzers used by the project without warnings and errors X3. The modified code is available under the configuration management system with a new version number for the specified CI
If these conditions are fulfilled then the review process terminates.

Which of the following characteristics of a formal review is missing in this description? Number of correct responses: 1
Options
A Metrics for reporting on the review effectiveness, efficiency, and progress
B Defined entry and exit criteria
C Checklists to be used by the reviewers
D Deliverables such as reports, evaluation sheets or other review summary sheets
Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

5
Question
Which of the following statements describing the consequences of specifying test conditions at a detailed level is NOT true? Number of correct responses: 1
Options
A For system testing, the specification of test conditions at a detailed level, carried out early in the
project as soon as the test basis is established, can contribute to defect prevention
B The specification of test conditions at a detailed level can be effective when no formal requirements or other development work products are available
C In an environment where the test basis is continuously changing, it is recommended to specify test conditions at a detailed level in order to achieve a better maintainability
D The specification of test conditions at a detailed level can require the implementation of an adequate level of formality across the team
Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

Finish Practice?

Are you sure you want to finish? This will end your practice session.