Official Bank 0/60

ISTQB-BCS Certified Tester Advanced Level- Test Analyst (2012) (TA12) - BCS Exam Questions

Last updated on June 20, 2026

97% Exam Compliance
60 Total Questions
1
Question
Working together with the test manager during test planning, which of the following activities is NOT expected to be performed by the test analyst? [K2] 1 credit
Options
A Review the test estimates of the test manager
B Organize adequate test resources
C Being involved in risk management sessions
D Review the test plan for non-functional testing
Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

2
Question
A temperature unit holds the temperature between 10 degrees Celcius and –10 degrees Celcius. If the temperature drops below –10 or rises above 10 then an alarm rings. Boundary Value Analysis tests are drawn up using the approach of two test cases per boundary. The temperatures to be tested are: [K3] 2 credits
Options
A 11, 9, -9, -11
B 11, 10, -11, -10
C 10, 9, -9, -10
D 11, 10, 9, -11, -10, -9
Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

3
Question
How many invalid test cases can be identified from the “Route Calculation” state table provided? You may assume all actions are different and independent. [K3] 3 credits
Options
A 6
B 102
C 12
D 8
Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

4
Question
A company wants to develop a web site to implement an on-line sales channel. The company has decided to do some usability testing, but resources are limited. The usability testing has therefore to be done as efficient as possible. Which THREE techniques would you recommend? [K4] 3 credits, 2 out of 3 correct 1 credit
Select 3
Options
A Use case testing
B SUMI
C Heuristic evaluation
D Equivalence partitioning
E Pairwise testing
G. Exploratory testing
F Usability laboratory
Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

5
Question
You are working as a tester on a project to develop a point-of-sales system for grocery stores. Which of the following is a product risk that could be identified for such a system? [K3] 2 credits
Options
A An excessively high number of defect fixes fail during re-testing
B The arrival of a more reliable competing product on the market
C Failure to accept allowed credit cards
D Delivery of an incomplete test release to the first cycle of system test
Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

Finish Practice?

Are you sure you want to finish? This will end your practice session.