Question
What is the schedule performance index (SPI) if the planned value (PV) is $100, the actual cost (AC) is
$150, and the earned value (EV) is $50?
Options
A 0.50
B 1.50
C 0.67
D 2.00
Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

2
Question
In which Knowledge Area is the project charter developed?
Options
A Project Cost Management
B Project Time Management
C Project Scope Management
D Project Integration Management
Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

3
Question
Which of the following is a statistical concept that calculates the average outcome when the future includes scenarios that may or may not happen?
Options
A Sensitivity analysis
B Modeling and simulation
C Three-point estimate
D Expected monetary value analysis
Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

4
Question
Which of the following is a narrative description of products, services, or results to be delivered by a project?
Options
A Project statement of work
B Accepted deliverable
C Business case
D Work performance information
Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

5
Question
Which of the following tools or techniques is used for Estimate Activity Durations?
Options
A Critical path method
B Precedence diagramming method
C Rolling wave planning
D Parametric estimating
Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

Finish Practice?

Are you sure you want to finish? This will end your practice session.