1
Question
Which tool and technique identifies inefficient and ineffective policies, processes and procedures?
Options
A Scope audits
B Control chart
C Quality audits
D Scope reviews
Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

2
Question
Which schedule development tool and technique produces a theoretical early start date and late start date?
Options
A Critical path method
B Variance analysis
C Schedule compression
D Schedule comparison bar charts
Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

3
Question
Which process involves aggregating the estimated costs of the individual schedule activities or work packages?
Options
A Cost baseline
B Cost forecasting
C Cost budgeting
D Cost variance
Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

4
Question
Given the following values, what is the calculated expected activity cost (CE) when using PERT?
CO = $7,000
CM = $10,500
CP = $11,000
Options
A $ 4,750
B $ 9,500
C $11,500
D $10,000
Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

5
Question
Which tool and technique uses a statistical relationship between historical data and other variables to calculate estimates?
Options
A Analogous estimating
B Parametric estimating
C Three-point estimates
D Bottom-up estimating
Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!