BCS Foundation Certificate in Project Management Exam (PM1-77) - BCS Actual Exam Questions
Last updated on April 11, 2026
Surveys have shown that the primary skill needed to be a project manager is communication skill. The typical project manager spends approximately ______ percent of his or her time communicating.
40-50
50-60
90-95
75-90
60-75
to join the discussion
No discussions yet. Be the first to ask!
Delete Comment
Are you sure? This action cannot be undone.
If a project manager is using observation and conversation to help control the project, she must be involved in which process?
Develop Project Team
Distribute Information
Manage Stakeholder Expectations
Manage Project Team
to join the discussion
No discussions yet. Be the first to ask!
Delete Comment
Are you sure? This action cannot be undone.
Which of the following is a conflict resolving technique that emphasizes areas of agreement rather than areas of difference?
Withdrawing/Avoiding
Forcing
Collaborating
Smoothing/Accommodating
to join the discussion
No discussions yet. Be the first to ask!
Delete Comment
Are you sure? This action cannot be undone.
What is an objective of the Developing Project Team Process?
Feelings of trust and improved cohesiveness
Ground rules for interaction
Enhanced resource availability
Functional managers become more involved.
to join the discussion
No discussions yet. Be the first to ask!
Delete Comment
Are you sure? This action cannot be undone.
Which of the following is the definition of a project?
Temporary endeavor undertaken to create a temporary business process or product
Temporary endeavor undertaken to create a unique product, service, or result
Permanent endeavor that produces repetitive outputs
Temporary endeavor that produces repetitive outputs
to join the discussion
No discussions yet. Be the first to ask!
Delete Comment
Are you sure? This action cannot be undone.
Finish Practice?
Are you sure you want to finish? This will end your practice session.