During the execution phase, what can a change manager do to ensure the most effective use of people?

Options
A

Integrate human resources with the change to give input on how to execute

B

Implement a controlled spending request and approval process

C

Establish a process to monitor physical resources and their performance

D

Implement a process for creating, storing, and sharing documents and reports

Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

2
Question

Sponsors play a critical role for change success. Which of the following statements best defines sponsorship?

Options
A

Sponsors are accountable for the realization of benefits for the change

B

Sponsors are part of the top senior executives' level of the organization

C

Sponsors directly contribute to the change

D

Sponsors can positively influence the change

Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

3
Question

What is a recommended practice for aligning stakeholders around benefits and value of a change?

Options
A

Conduct a risk assessment of the dangers and impediments to implementing the change

B

Analyze the learning capabilities of the organization impacted by the change

C

Use both formal and informal channels to communicate the business rationale for the change

D

Evaluate the final outcome of the change against the original objectives of the change

Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

4
Question

The first two weeks of a large and complex change project is underway and things seem to be going okay. What have you developed so that you can be sure the change is on track?

Options
A

Stakeholder engagement strategy

B

Project management plan

C

Risk mitigation strategy

D

Measurement and benefits realization strategy

Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

5
Question

How is sponsorship most successful during change?

Options
A

Sponsors build awareness with stakeholders regarding the need for change and participate throughout the project

B

The role of the sponsor is clearly defined and agreed upon by the sponsor and change lead

C

The sponsor is coached and supported throughout the change management effort

D

The sponsor is well equipped to deliver communications and key messages about the change

Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

Finish Practice?

Are you sure you want to finish? This will end your practice session.