1
Question
What are two anti-patterns for the IP Iteration? (Choose two.)
Select 2
Options
A To wait for the IP Iteration to fix defects
B To minimize lost capacity when people are on vacation or holidays
C To plan work for the IP lteration during P Planning
D To allow for sufficient capacity in the Program Roadmap
E To ensure all Stories and teams' Pl plans are completed prior to the IP Iteration
Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

2
Question
Which statement is true about nonfunctional requirements?
Options
A They stay in the Portfolio Backlog until implementation capacity is available
B They are split into Features and acceptance criteria is established
C They operate as constraints on the design of the system
Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

3
Question
What is one activity the Release Train Engineer (RTE) performs before an upcoming PI?
Options
A Ensures at least 30% of the ART Backlog is allocated to Enabler Features
B Provides approval and sign-off for draft Team Backlogs
C Allocates time in the Coach Sync for Product Management to socialize with the teams on the Features
D Facilitate ART Backlog prioritization with Product Management and other stakeholders
Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

4
Question
Which SAFe tool might the RTE use to identify areas for an ART to improve how its Con-tinuous Delivery Pipeline (CDP) functions?
Options
A Architectural runway program backlog enablers
B Agile Product Delivery core competency assessment
C Facilitate a CDP sync every iteration
D Conduct empathy interviews with system architects/engineers
Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

5
Question
The Agile Release Train (ART) is near the end of the final Iteration of their first Program Increment. Integration into staging is more challenging than estimated. They add a week to the Innovation and Planning (IP) Iteration for integration and testing. Why is this a bad idea?
Options
A It decreases job satisfaction by removing autonomy and purpose
B Overall train velocity goes up and the time-to-market goes down
C It substantially decreases the predictability of the Solution Intent
D It reduces the overall predictability established through cadence and synchroniza-tion
Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!