Official Bank 0/1320

Certified Associate in Project Management (CAPM) Exam (CAPM) - PMI Exam Questions

Last updated on June 20, 2026

97% Exam Compliance
1320 Total Questions
1
Question
A new project was approved by the project management office (PMO), and the scope of the project is to build a new detachable classroom. What delivery method and artifacts should the project manager use to deliver this project?
Options
A Linear project management; project schedule and work breakdown structure (WBS)
B Adaptive project management; project schedule and work breakdown structure
C Adaptive project management; project schedule and project backlog
D Linear project management; project schedule and project backlog
Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

2
Question
Cost baseline is an output of which of the following processes?
Options
A Estimate Costs
B Determine Budget
C Estimate Activity Resources
D Control Costs
Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

3
Question
Project governance refers to framework.......which of the following is a portfolio? Pioject governance refers lo framework, functions, and processes that guide project management activates with a defined hierarchy between projects, programs and poctfotos. According to this hierarchy, which ot Die following is a portfolio?
Options
A A portfolio is a group of projects managed by the same project manager.
B A portfolio is the mam project of the company, supervised directly by the CEO.
C A portfolio is a group of related proiecls, programs, subsidary portfolios, and operation*, thai provides similar products or services.
D A portfolio is a group of projects, programs, subsidiary portfolios and operations managed together to achieve strategic objectives.
Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

4
Question
The primary purpose of the stakeholder register is to:
Options
A Maintain a list of all project stakeholders
B Maintain lessons learned earlier in the project
C Document change requests and their status
D Record stakeholder issues on the project
Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

5
Question
Funding limit reconciliation is a tool and technique used in which process?
Options
A Estimate Costs
B Determine Budget
C Control Budget
D Control Costs
Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

Finish Practice?

Are you sure you want to finish? This will end your practice session.