How often should Scrum Team membership change?
Options
A As needed, while taking into account a short term reduction in productivity.
B Never, because it reduces productivity.
C Every Sprint to promote shared learning.
D As needed, with no special allowance for changes in productivity.
Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

2
Question
When a Development Team determines that it will not be able to finish the complete forecast, who has to be present when reviewing and adjusting the Sprint work selected? (Choose the best answer.)
Options
A The Product Owner and all stakeholders.
B The Development Team.
C The Scrum Master, project manager and Development Team.
D The Product Owner and the Development Team.
Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

3
Question
Which three of the following are time-boxed events in Scrum? (Choose the best three answers.)
Select 3
Options
A Release Planning.
B Sprint Testing.
C Release Retrospective.
D Sprint Planning.
E Sprint Retrospective.
F Sprint 0.
G. Daily Scrum.
Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

4
Question
A properly functioning Scrum Team will have at least one Release Sprint and may well have several.
Options
A True
B False
Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

5
Question
Who can abnormally terminate a Sprint?
Options
A The Development Team or its members.
B The Scrum Master
C The Stakeholders
D The Product Owner
Discussion (0 comments)

to join the discussion

Community Discussion

No discussions yet. Be the first to ask!

Finish Practice?

Are you sure you want to finish? This will end your practice session.